03/21/2024 | Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 110 |
10/03/2023 | Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. | 8 |
09/07/2023 | Response to Staff 2nd Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 7 |
08/18/2023 | Response to Staff's 1st Data Request, Green Chapel electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. | 3 |
07/17/2023 | Notice of Proof of Compliance with Green Chapel Extension 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 22 |
07/12/2023 | Letter of Notification Application for the Green Chapel Extension 138 kV Transmission Line Project - Part 3 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 122 |
07/12/2023 | Letter of Notification Application for the Green Chapel Extension 138 kV Transmission Line Project - Part 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 124 |
07/12/2023 | Letter of Notification Application for the Green Chapel Extension 138 kV Transmission Line Project - Part 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 122 |
07/11/2023 | In the Matter of the Pre-Application Notification Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 368 |