Date Filed | Summary | Pages |
09/21/2023 | Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 183 |
02/27/2023 | Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 180 |
02/27/2023 | Start of Construction Notice electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
02/14/2023 | Service Notice. | 2 |
02/14/2023 | Staff Report of Investigation electronically filed by Ms. Justine Patmon on behalf of Staff of the OPSB. | 7 |
11/22/2022 | Letter of Notification Application for the Anguin - Brie 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 331 |
11/21/2022 | In the Matter of the Pre-Application Notification Letter for the Anguin-Brie 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |