Date Filed | Summary | Pages |
09/20/2024 | Notice of Certificate Compliance with Condition 40 – Final Complaint Resolution Plan electronically filed by Christine M.T. Pirik on behalf of Blossom Solar, LLC. | 5 |
09/05/2024 | Notice of Certificate Compliance Condition 22 regarding Update to Decommissioning Plan filed on March 29, 2024 electronically filed by Christine M.T. Pirie on behalf of Blossom Solar, LLC. | 20 |
03/29/2024 | Notice - Certificate Compliance Condition 22 – Decommissioning Plan electronically filed by Christine M.T. Pirik on behalf of Blossom Solar, LLC. | 20 |
06/28/2023 | Notice of Withdrawal of Counsel electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC. | 3 |
06/23/2023 | Notice of Change in Address, Point of Contact, and Ownership electronically filed by Mr. Matthew C. McDonnell on behalf of Blossom Solar, LLC. | 2 |
06/23/2023 | Notice of Appearance for Blossom Solar, LLC electronically filed by Mr. Matthew C. McDonnell on behalf of Blossom Solar, LLC. | 3 |
05/18/2023 | Opinion & Order issuing a certificate of environmental compatibility and public need to Blossom Solar, LLC for the construction, operation, and maintenance of the solar-powered electric generation facility, subject to the conditions set forth in the Stipulation and consistent with this Opinion and Order electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board. | 59 |
05/18/2023 | Service Notice. | 4 |
03/14/2023 | PUCO Exhibit Filing - Company Exhibits 4 and 5 filed by Karen Sue Gibson on behalf of Armstrong & Okey. | 201 |
03/13/2023 | Transcript for Hearing Held on March 7, 2023 at 10:03 a.m. before Administrative Law Judge Ms. Greta See, at the Public Utility Commission of Ohio, Ohio Power Siting Board, 180 E. Broad Street, Room 11-C, Columbus, Ohio 43215 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs. | 19 |
02/27/2023 | Direct Testimony of Patrick Buckley electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC. | 30 |
02/27/2023 | Direct Testimony of Mark Bonifas electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC. | 19 |
02/27/2023 | Direct Testimony of John Woods electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC. | 9 |
02/27/2023 | Direct Testimony of Brooke Harrison electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC. | 9 |
02/27/2023 | Prefiled Testimony of James S. O'Dell on Behalf of the Public Utilities Commission of Ohio, Power Siting Department, electronically filed by Mrs. Kimberly M. Naeder on behalf of OPSB. | 7 |