Date Filed | Summary | Pages |
02/02/2023 | Case Action Form closing the case with an effective date of 02/02/23 filed by Jeffrey R. Jones on behalf of PUCO Staff. | 1 |
09/16/2021 | Service Notice. | 2 |
09/16/2021 | Entry dismissing this matter at the request of the applicant, AEP Ohio Transmission Company, Inc., electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board. | 4 |
08/30/2021 | Notice of Withdrawal electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
06/10/2021 | Proof of Compliance and Associated Exhibits for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. | 21 |
06/03/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 51 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 2201-2300 b electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 101 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 2301-2432 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 133 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 2100-2200 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 101 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 1501-1800 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 301 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 1201-1500 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 302 |
05/28/2021 | Letter of Notification application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 1001-1200 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 201 |
05/28/2021 | Letter of Notification application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 801-1001 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 201 |
05/28/2021 | Letter of Notification application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 601-800 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 201 |
05/28/2021 | Letter of Notification Application for the Tidd-Sunnyside 138 kV Transmission Line Rebuild Project 401-600 B electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 201 |