10/03/2022 | Notification of Completion of Construction and In-Service Date electronically filed by Mrs. Debbie L. Gates on behalf of Duke Energy Ohio, Inc. and D'Ascenzo, Rocco O. Mr. and Kingery, Jeanne W. and Vaysman, Larisa and Akhbari, Elyse. | 2 |
09/02/2021 | Letter Accepting Required Conditions electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 3 |
08/31/2021 | Service Notice. | 3 |
08/31/2021 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
08/24/2021 | Ohio History Connection Concurrence Letter electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 3 |
08/18/2021 | Notice of OEPA Isolated Wetland Permit electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio, Mr. Rocco O. D'Ascenzo and Ms. Jeanne W. Kingery. | 4 |
07/23/2021 | Correspondence submitting supplemental information to the application electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio, Rocco D'Ascenzo and Ms. Jeanne W. Kingery. | 3 |
06/15/2021 | Proof of Service electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 9 |
06/09/2021 | Ohio Department of Natural Resources Correspondence electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 6 |
06/08/2021 | Construction Notice for the Half Acre Substation Transmission Line Relocation Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 150 |
06/03/2021 | In the Matter of the Pre-Application Notification Letter for New Half Acre Substation Transmission Line Relocation electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. (2 pages) | 2 |