Date Filed | Summary | Pages |
04/29/2021 | Notification of Construction Completion Date for the Morse Road - Genoa 138 kV Line (Structures 1-4) Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 2 |
03/08/2021 | Notice of Proof of Compliance with Condition 2 for the Morse Road - Genoa 138 kV Line (Structures 1-4) electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 10 |
02/16/2021 | Start of Construction Notice for the Morse Road - Genoa 138 kV Line (Structures 1-4) Project as of February 23, 2021 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 2 |
02/11/2021 | Notice of Proof of Compliance with Condition 2 and associated exhibits for the Morse Road - Genoa 138 kV Line (Structures 1-4) electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 147 |
01/19/2021 | Proof of Compliance with Conditions and associated exhibits for the Morse Road - Genoa 138 kV Line (Structures 1-4) Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 14 |
10/15/2020 | Service Notice. | 3 |
10/15/2020 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
08/03/2020 | Notice of Proof of Compliance and associated exhibits for the Morse Road - Genoa 138 kV Line (Structures 1-4) Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 8 |
07/23/2020 | Construction Notice (Structures 1 - 4) electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 318 |
07/16/2020 | In the Matter of the Pre-Application Notification Letter for the Compatibility and Public Need for the Morse Road – Genoa 138 kV Line Project (Structure 1-4) electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 2 |