Case Title: Kammer-Dumont 765 kV Transmission Line Cut In
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 5/28/2020
Date Closed:
Printable Docket Card Service List
View All
1 - 12 of 12 documents 1 /  1 
Date FiledSummaryPages
03/25/2022Notice of Proof of Compliance with Condition 4 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.34
07/12/2021Notice of June 23, 2021 In-Service Date electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company.2
10/14/2020Notice Third Proof of Compliance with Condition 4 letter and associated exhibit for the Kammer-Dumont 765 kV Transmission Line Cut In Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.3
10/01/2020Second Proof of Compliance with Condition 4 letter and associated exhibit for the Kammer-Dumont 765 kV Transmission Line Cut In Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.4
09/14/2020Notice of Proof of Compliance with Condition 4 electronically filed by Tanner Wolffram on behalf of Ohio Power Company.171
09/02/2020Notice Start of Construction Notice for the Kammer-Dumont 765 kV Transmission Line Cut In electronically filed by Tanner Wolffram on behalf of Ohio Power Company.2
08/20/2020Service Notice2
08/20/2020Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff.6
07/08/2020Notification of State Historic Preservation Office Concurrence and associated exhibit for the Kammer-Dumont 765 kV Transmission Line Cut In Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.3
06/08/2020Proof of Compliance and associated exhibits for the Kammer-Dumont 765 kV Transmission Line Cut In Project- PART 1 electronically filed by Tanner Wolffram on behalf of Ohio Power Company.11
06/08/2020Notice of Proof of Compliance and associated exhibits for the Kammer-Dumont 765 kV Transmission Line Cut In Project- PART 2 electronically filed by Tanner Wolffram on behalf of Ohio Power Company.6
05/28/2020In the matter of the Construction Notice Application for the Kammer-Dumont 765 kV Transmission Line Cut In electronically filed by Tanner Wolffram on behalf of Ohio Power Company.30
 