Date Filed | Summary | Pages |
08/17/2021 | Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
05/15/2020 | Service Notice | 2 |
05/15/2020 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
03/11/2020 | Service Notice | 1 |
02/25/2020 | Notice Proof of Compliance Letter and associated exhibits for the Shawtown Switch – Hancock Wood Co-Op 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 21 |
02/21/2020 | Construction Notice for the Shawtown Switch-Hancock Wood Co-Op 138 kV Transmission Line Project- PART 1 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 29 |
02/21/2020 | Construction Notice for the Shawtown Switch-Hancock Wood Co-Op 138 kV Transmission Line Project- PART 1 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 26 |
02/18/2020 | In the matter of the Pre-Application Notification Letter for the Shawtown Switch – Hancock Wood Co-Op 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 3 |