Date Filed | Summary | Pages |
11/04/2021 | Construction Completion Notification Letter electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. | 2 |
06/15/2020 | Notice of Issuance of Right of Entry and Accompanying Documents electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 13 |
04/28/2020 | Notice of Docketing of Approvals from the Ohio Department of Transportation, Office of Aviation electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 27 |
04/22/2020 | Notice of Approval of Flood plain Permit for Trumbull County with Copy of Approval Documents electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 22 |
04/22/2020 | Notice of Approval of Floodplain Permit for Portage County with Copy of Approval Documents electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 40 |
04/16/2020 | Service Notice | 2 |
04/16/2020 | Opinion, Order and Certificate ordering a certificate be issued to ATSI for the construction, operation and maintenance of the Hanna Newton Falls rebuild project electronically filed by Kelli C. King on behalf of Ohio Power Siting Board. | 11 |
04/02/2020 | Notice of Issuance of Right of Way Work Permit in Trumbull County, Ohio electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 5 |
03/31/2020 | Notice of the Docketing of ODOT Permits for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 32 |
03/23/2020 | Notice of Approval by Portage and Trumbull Counties of Stormwater Pollution Prevention Plan for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 5 |
03/20/2020 | Administrative Law Judge Entry granting limited certificate authority, as detailed herein. electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Administrative Law Judge, The Ohio Power Siting Board. | 11 |
03/13/2020 | Letter of Notification stating that construction will commence on March 20, 2020 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
03/06/2020 | Notice of Docketing of Stormwater Pollution Prevention Plan per Recommended Condition in Staff Report of Investigation (Part 2 of 2) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 224 |
03/06/2020 | Notice of Docketing of Stormwater Pollution Prevention Plan per Recommended Condition in Staff Report of Investigation (Part 1 of 2) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 66 |
02/25/2020 | Service Notice | 2 |