Date Filed | Summary | Pages |
02/06/2019 | Notification for Morgan 1689 Separation Project was completed on and the facility in-service date was February 1, 2019 electronically filed by Carys Cochern on behalf of Duke Energy. | 2 |
11/27/2018 | Notice that Duke Energy Ohio, Inc. adopts and accepts required condition electronically filed by Carys Cochern on behalf of Kingery, Jeanne W Ms. | 2 |
11/21/2018 | Service Notice | 2 |
11/21/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
11/13/2018 | Notice of Proof of Service of Duke Energy Ohio, Inc. electronically filed by Carys Cochern on behalf of Kingery, Jeanne W Ms. | 6 |
11/06/2018 | Construction Notice for the Morgan 1689 Separation Project
electronically filed by Carys Cochern on behalf of Duke Energy. | 60 |
11/01/2018 | In the matter of the Pre-Application Notification Letter for the Morgan 1689 Separation Project electronically filed by Carys Cochern on behalf of Duke Energy. | 2 |