Date Filed | Summary | Pages |
05/24/2021 | Notice of Start of Construction and In-Service Date for the Seaman-Sardinia 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
04/28/2020 | Notice of Adjustments for Seaman-Sardinia 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 4 |
02/21/2019 | Service Notice | 2 |
02/21/2019 | Opinion, Order, and Certificate stating that the Stipulation be approved and adopted and a certificate be issued to AEP Ohio Transco for the construction, operation, and maintenance of the electric transmission line along the preferred route. | 30 |
11/19/2018 | Transcript In the Matter of the Application of AEP Ohio Transmission Company, Inc. for a Certificate of Environmental Compatibility and Public Need for the Buckley Road-Fremont Center 138kV Transmission Line Project, hearing held on November 5th, 2018. electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and James, Romaine | 14 |
10/31/2018 | Transcript for hearing held on 10/11/18 at Brown County Public Library - Sardinia Branch, 13309 Purdy Road, Sardinia, Ohio before Administrative Law Judge Daniel Fullin filed by K. Graff on behalf of Elite Reporting Agency. | 13 |
10/24/2018 | Testimony of Jon C. Pawley electronically filed by Ms. Tonnetta Scott on behalf of PUC. | 6 |
10/22/2018 | Testimony (Direct Testimony of Ronald M. Howard, Jr. in Support of the Stipulation and Recommendation) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 29 |
10/22/2018 | Stipulation and Recommendation electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 21 |
10/12/2018 | List of Issues electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 7 |
10/11/2018 | Proof of Notification Seaman-Sardinia 138kV Transmission Line Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 15 |
09/26/2018 | Service Notice | 3 |
09/26/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 43 |
08/21/2018 | Service Notice | 1 |
08/21/2018 | Administrative Law Judge Entry setting procedural schedule in accordance with Paragraph 11 and scheduling hearings at the times and places designated in Paragraph 7 - electronically filed by Sandra Coffey on behalf of Daniel Fullin, Attorney Examiner, Public Utilities Commission of Ohio. | 6 |