Date Filed | Summary | Pages |
02/04/2019 | Construction Notice of Aetna (West Akron) 138 kV and Babb - West Akron 138 kV Transmission Lines Structure Replacement Project was completed on January 29. 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
03/23/2018 | Construction Notice advising that construction will commence on March 23, 2018 and notification will be given when project is complete filed on behalf of FirstEnergy Service Company by N. Bryksenkova. | 1 |
02/01/2018 | Service Notice | 2 |
02/01/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
01/17/2018 | Construction Notice Application of ATSI proposing to replace one transmission structure (Tower #672) on the Aetna (West Akron) 138 kV & Babb - West Akron 138kV Transmission Lines due to erosion caused by a nearby stream, the Project area is located in the city of Akron, Summit County, Ohio filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 51 |
12/14/2017 | In the matter of the Notice of Filing of Pre-Application Letter electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |