DIS - Case Record for 17-2312-EL-BNR Skip to main content

Case Record For:

17-2312-EL-BNR

File a Public Comment
Case Title: Chrysler-Dowling 138 kV Transmission Line Tap Final Span Installation to New First Solar Substation Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 11/7/2017
Date Closed:
Printable Docket Card Service List
View All
1 - 8 of 8 documents 1 /  1 
Date FiledSummaryPages
01/17/2018Construction Notice regarding completion of projects filed by W. Beutler on behalf of FirstEnergy Service Company.1
12/06/2017Notice that construction on both projects will commence on December 11, 2017 filed by W. Beutler on behalf of FirstEnergy Service Company.1
11/15/2017Service Notice2
11/15/2017Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
11/13/2017Application previously filed electronically in two parts on 11/8/17 filed by W. Beutler on behalf of American Transmission Systems, Inc.63
11/08/2017Application of The Toledo Edison Company for a Certificate of Environmental Compatibility and Public Need (2 of 2) electronically filed by Mr. Robert J Schmidt on behalf of The Toledo Edison Company32
11/08/2017Application of The Toledo Edison Company for a Certificate of Environmental Compatibility and Public Need (1 of 2) electronically filed by Mr. Robert J Schmidt on behalf of The Toledo Edison Company33
11/07/2017In the matter of the Pre-Application Notification Letter electronically filed by Mr. Robert J. Schmidt on behalf of The Toledo Edison Company.2
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: