Date Filed | Summary | Pages |
01/17/2018 | Construction Notice regarding completion of projects filed by W. Beutler on behalf of FirstEnergy Service Company. | 1 |
12/06/2017 | Notice that construction on both projects will commence on December 11, 2017 filed by W. Beutler on behalf of FirstEnergy Service Company. | 1 |
11/15/2017 | Service Notice | 2 |
11/15/2017 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
11/13/2017 | Application previously filed electronically in two parts on 11/8/17 filed by W. Beutler on behalf of American Transmission Systems, Inc. | 63 |
11/08/2017 | Application of The Toledo Edison Company for a Certificate of Environmental Compatibility and Public Need (2 of 2) electronically filed by Mr. Robert J Schmidt on behalf of The Toledo Edison Company | 32 |
11/08/2017 | Application of The Toledo Edison Company for a Certificate of Environmental Compatibility and Public Need (1 of 2) electronically filed by Mr. Robert J Schmidt on behalf of The Toledo Edison Company | 33 |
11/07/2017 | In the matter of the Pre-Application Notification Letter electronically filed by Mr. Robert J. Schmidt on behalf of The Toledo Edison Company. | 2 |