Date Filed | Summary | Pages |
12/19/2018 | Notice that construction on both projects was completed on December 3, 2018 filed on W. Beutler on behalf of FirstEnergy Service Company. | 1 |
04/13/2018 | Correspondence providing supplemental information concerning an engineering change to the the construction of the London-Tangy 138 kV Transmission Line Relocation and Tangy Substation Expansion Project filed on behalf of FirstEnergy Service Company by W. Beutler. | 2 |
09/11/2017 | Construction Notice that project will commence on September 18, 2017 filed by W. Beutler on behalf of FirstEnergy Service Company. | 1 |
08/24/2017 | Service Notice | 2 |
08/24/2017 | Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. | 4 |
06/01/2017 | Construction Notice for the London-Tangy 138 kV Transmission Line Relocation and Tangy Substation Expansion Project filed on behalf of FirstEnergy Service Company by W. Beutler. | 49 |
05/25/2017 | In the matter of the pre-application notification letter for the London-Tangy 138 kV Transmission Line
Relocation And Tangy Substation Expansion Project. | 1 |