Date Filed | Summary | Pages |
01/17/2018 | Notification of In-Service Date electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
11/17/2017 | Notification of Start of Construction electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
09/07/2017 | Correspondence electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
09/06/2017 | Service Notice | 2 |
09/06/2017 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
09/01/2017 | Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
09/01/2017 | Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
08/31/2017 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 3 |
08/15/2017 | Letter of Notification (Part 4) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 29 |
08/15/2017 | Letter of Notification (Part 3) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 60 |
08/15/2017 | Letter of Notification (Part 2) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 63 |
08/15/2017 | Letter of Notification (Part 1) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 61 |
08/10/2017 | In the Matter of the Pre-Application Notification Letter for the Tidd-Wagenhals 138kV Transmission Line Extension Project electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |