Date Filed | Summary | Pages |
12/06/2019 | Case Action Form Close Case with and effective date of 12/6/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio | 2 |
08/26/2019 | Notice of Commencement and Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
08/26/2019 | Notice of Commencement and Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
06/23/2017 | Correspondence Acceptance of Staff Conditions 17-0633-EL-BLN (Lemaster-Lick) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
06/23/2017 | Service Notice | 2 |
06/23/2017 | Staff Report of Investigation filed by P. Donlon. | 4 |
04/28/2017 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 7 |
04/10/2017 | Notification of compliance electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
04/10/2017 | Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company | 2 |
04/03/2017 | Application continued: Letter of Notification 4 of 4 parts electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 3 |
04/03/2017 | Application continued: Letter of Notification 3 of 4 parts electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 96 |
04/03/2017 | Application continued: Letter of Notification 2 of 4 parts electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 28 |
04/03/2017 | In the matter of the Letter of Notification for the Lemaster-Lick 138kV Transmission Line Extension Project: 1 of 4 Parts electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 80 |