DIS - Case Record for 16-2212-EL-BNR Skip to main content

Case Record For:

16-2212-EL-BNR

File a Public Comment
Case Title: 138 kV Transmission Line Extensions to Holloway Substation Structure Replacement Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 11/17/2016
Date Closed:
Printable Docket Card Service List
View All
1 - 6 of 6 documents 1 /  1 
Date FiledSummaryPages
06/12/2017Construction Notice stating that project was completed on June 9, 2017.1
01/19/2017Construction Notice 138 kV Transmission Line Extensions To Holloway Substation Structure Replacement Project filed by William R Beutler on behalf of FirstEnergy Service Company. 1
01/10/2017Service Notice2
01/10/2017Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
12/23/2016Request of ATSI for an expedited review for the 138kV Transmission Line Extensions to Hollowway Substation Structure Replacement Project filed by W. Beutler.33
11/17/2016In the matter of the Notice of the Filing of the Pre-Application Notice Letter for Holloway Substation Structure Replacement Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.2
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: