Date Filed | Summary | Pages |
06/08/2018 | Notification of In-Service Date and Completion of Construction electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
02/09/2017 | Notification of Start of Construction for the Poston-Hocking 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
11/14/2016 | Acceptance of Staff's Conditions Poston-Good Hope #1 (Structure 71-Good Hope) electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. | 2 |
10/31/2016 | Staff Report of Investigation electronically filed by Yvonne W Cooper on behalf of Staff of OPSB. | 6 |
10/27/2016 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 4 |
10/26/2016 | Correspondence - Official Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
10/26/2016 | Correspondence - Public Notification Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
10/07/2016 | Letter of Notification Case 16-1486-EL-BLN Request for Expedited Treatment: LON for Poston-Good Hope # 1 138 kV Transmission Line Rebuild Project electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 107 |
08/18/2016 | In the matter of the Pre-Application Notification Letter (Poston-Good Hope) electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company | 2 |