Date Filed | Summary | Pages |
12/22/2016 | Letter stating that the date of the Completion of Construction for Inland Substation Expansion Project was December 19, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
04/01/2016 | Construction Notice informing the Commission that the Inland Substation Expansion Project, which was approved by the Board on
March 4, 2016, commenced on March 29, 2016 filed by N. Bryksenkova, Engineer on behalf of FirstEnergy Service Company. | 1 |
02/19/2016 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
02/11/2016 | Construction Notice filed by Nataliya Bryksenkova on behalf of FirstEnergy Corp. | 25 |
02/03/2016 | In the matter of the Notification of Pre-Application Letter for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |