Date Filed | Summary | Pages |
07/20/2016 | Notice that In service date for the Glen Karn ANR Interconnect was April 1, 2016 electronically filed by Mr. Joseph C Dean on behalf of Vectren Energy. | 2 |
09/16/2015 | Notification of the Start of Construction electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 2 |
07/30/2015 | Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. | 4 |
07/17/2015 | Request for expedited processing Vectren Energy Delivery of Ohio Proof of Payment of Expedited Fee electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 4 |
07/16/2015 | Request for Expedited Processing filed by M. Stahl on behalf of Vectren Energy Delivery of Ohio, Inc. | 1 |
07/15/2015 | Request of Vectren Energy Delivery of Ohio, Inc. for Expedited Treatment electronically filed by Melinda R. Stahl on behalf of Vectren Energy Delivery of Ohio. | 2 |
07/15/2015 | Application Cont. - Notice of Construction Application for the Glen Karn ANR Interconnect (part 7 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 37 |
07/15/2015 | Application Cont. - Notice of Construction Application for the Glen Karn ANR Interconnect (part 6 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 36 |
07/15/2015 | Application Cont. - Notice of Construction Application for the Glen Karn ANR Interconnect (part 5 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 12 |
07/15/2015 | Application Cont. - Notice of Construction Application for the Glen Karn ANR Interconnect (part 4 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 23 |
07/15/2015 | Application Cont. -Notice of Construction Application for the Glen Karn ANR Interconnect (part 3 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 37 |
07/15/2015 | Application Cont.. - Notice of Construction Application for the Glen Karn ANR Interconnect (part 2 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 52 |
07/15/2015 | In the matter of the Notice of Construction Application for the Glen Karn ANR Interconnect (part 1 of 7) electronically filed by Melinda R Stahl on behalf of Vectren Energy Delivery of Ohio. | 22 |