Date Filed | Summary | Pages |
02/15/2017 | Case Action Form closing cases effective 2/15/2017 filed by S. Parrot. | 1 |
05/03/2016 | Notice of Change of Address for counsel for the Public Utilities Commission of Ohio, effective May 9, 2016. electronically filed by Kimberly L Keeton on behalf of Public Utilities Commission of Ohio. | 3 |
02/10/2016 | Opinion and Order that the Stipulation be adopted and approved. | 11 |
02/10/2016 | Service Notice | 2 |
09/10/2015 | PUCO Exhibit Filing | 10 |
09/10/2015 | Transcript in the matter of Glenwood Energy of Oxford, Inc. hearing held on 09/01/15 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Cunningham, Cindy. | 14 |
08/27/2015 | Stipulation and Recommendation submitted by Assistant Attorney General Werner Margard. electronically filed by Kimberly L Keeton on behalf of Public Utilities Commission of Ohio. | 8 |
07/02/2015 | Report by the Staff of the PUCO on Glenwood Energy of Oxford, Inc. Audit of the Percentage of Income Payment Plan Mechanisms
for the period January 2013 through December 2014 filed by PUCO Staff. | 6 |
02/19/2015 | Service Notice | 1 |
02/19/2015 | Entry ordered, That the GCR audit reports for Foraker, Eastern, Glenwood, Pike, Southeastern, and Waterville for the audit periods set forth in Finding (3) be filed with the Commission, as set forth in Finding (5). It is, further. ordered, That a public hearing shall be conducted in each of the GCR proceedings, consistent with the findings herein, on the dates specified in Finding (6). It is, further, ordered That Foraker, Eastern, Glenwood, Pike, Southeastern, and Waterville publish legal notice in accordance with Finding (7). It is, further, ordered, That the direct testimony be filed in the GCR cases consistent with Finding (8). It is, further, ordered, That the UEX audit reports for Eastern, Glenwood, Pike, and Waterville for the audit periods set forth in Finding (9) be filed with the
Commission, as set forth in Finding (10). It is, further, ordered, That the PIPP audit reports for Eastern, Glenwood, Pike, and
Southeastern for the audit periods set forth in Finding (11) be filed with the
Commission, as set forth in Finding (12). | 7 |
02/13/2015 | In the matter of the application of Glenwood Energy of Oxford, Inc. for approval of an adjustment to its Interim Emergency and Temporary PIPP Plan Rider Rate. | 1 |
|