Date Filed | Summary | Pages |
12/05/2016 | Construction Notice that project was completed on November 30, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
03/21/2016 | Notice that construction on the Avon-Beaver No.1 and No.2 345 kV Transmission Line Extensions to Lake Avenue Substation Project was approved by the Board on May 13, 2015, commenced on March 11, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
05/06/2015 | Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB. | 3 |
04/01/2015 | Construction notice of American Transmission System Incorporated for Avon-Beaver No. l and No. 2 345 kV Transmission Line Extensions to Lake Avenue Substation Project filed by N. Bryksenkova. | 12 |
03/31/2015 | In the matter of the Notification of Construction (Construction Notice) for the Avon-Beaver No 1 and No 2 345 kv Transmission Line Extensions to Lake Avenue Substation electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 13 |