06/08/2015 | Letter of notification stating construction on this project was completed on May 28, 2015 filed on behalf of FirstEnergy Service Company by T. Turner. | 1 |
10/27/2014 | Notice that construction on this project is expected to begin on approximately November 3, 2014. | 1 |
10/06/2014 | Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB. | 4 |
09/22/2014 | Notice of payment to the Ohio Power Siting Board Fund for application for the Leroy Center Switching Station 138 kV Transmission Lines Reconfiguration Project filed on behalf of American Transmission System, Incorporated by T. Turner. | 2 |
09/22/2014 | In the matter of the Construction Notice of American Transmission Systems Incorporated for project - Leroy Center Switching Station 138 kV Transmission Lines Reconfiguration Project. | 22 |