Date Filed | Summary | Pages |
01/13/2014 | Letter of Notification that construction was completed on the London-Tangy 69 kV Transmission Line Project on approximately January 4, 2014, filed by Travis Turner on behalf of FirstEnergy Service Company. | 1 |
12/03/2013 | Letter stating that construction on London-Tangy 69 kV Transmission Line Tap to Jefferson Industries Substation Project is expected to begin on approximately December 2, 2013 filed by T. Turner on behalf of FirstEnergy Service Company. | 1 |
11/20/2013 | Proof of Publication. (Madison County) | 3 |
11/18/2013 | Notice of Withdrawal of Motion for Partial Waiver electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 3 |
11/13/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 3 |
11/01/2013 | Motion and memorandum in support for Partial Wavier of Time Period for Review electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 7 |
11/01/2013 | In the matter of the application of American Transmission Systems, Incorporated for Letter of Notification. | 50 |