Date Filed | Summary | Pages |
03/20/2014 | Response to the Letter of Notification that the Evergreen-Ivanhoe Project was completed on approximately March 13, 2014 filed by T. Turner on behalf of FirstEnergy Service Company. | 1 |
10/24/2013 | Report of investigation electronically filed by Mr. Adam S. Bargar on behalf of Staff of OPSB. | 3 |
08/06/2013 | Letter of notification - Evergreen-Ivanhoe 138 kV Transmission Line Tap to Ohio Star Forge Substation. | 19 |
08/06/2013 | In the matter of the Letter of Notification for the Evergreen-Ivanhoe 138 kV Transmission Line Tap to Ohio Star Forge Substation. | 18 |