DIS - Case Record for 13-0301-RR-STP Skip to main content

Case Record For:

13-0301-RR-STP

Case Title: NORFOLK SOUTHERN RAILWAY COMPANY/THE VILLAGE OF ASHVILLE AT GRIGGS
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: STP-State funded warning projects
Date Opened: 1/25/2013
Date Closed: 8/7/2017
Printable Docket Card Service List
View All
1 - 15 of 24 documents 1 /  2 
Date FiledSummaryPages
08/07/2017Case Action Form closing case with an effective date of 08/07/17, electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.2
08/07/2017Memo In the Matter of a Request to Install Active Grade Crossing Warning Devices at Griggs Street, in the Village of Ashville, Pickaway County. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.6
07/15/2015Memorandum recommending Staff grant the requested extension of time to complete this project, filed by J. Henry, Rail Division.6
07/08/2015Service Notice2
07/08/2015Entry ordered, that NS's request for an extension of time to complete the project is granted in accordance with finding 8. It is, further, ordered. that NS complete the project by November 13, 2015. 3
06/26/2015Request for Extension of Construction Deadline and memorandum in support electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.4
02/11/2015Service Notice2
02/11/2015Entry ordering that NS's request for an extension of time to complete the project is granted in accordance with finding (5) and that NS complete the project by July 13, 2015.2
02/06/2015Request for extension of construction deadline the Village of Ashville is scheduled to complete the roadway work by the first part of May and then NS will be able to complete the crossing work. NS is requesting a 5 month extension until July 13, 2015 filed by Staff6
01/29/2015Consent Request for Extension of Construction Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.4
08/20/2014Service Notice2
08/20/2014Entry granting NS's request for extension of time to complete the project by February 13, 2015.2
08/05/2014Memo stating that PUCO Rail Staff recommend that the Commission grant the extension request from Norfolk Southern Railway Company with Memorandum in Support filed by staff, J. Henry.5
07/30/2014Consent Request for Extension of Construction Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.4
02/05/2014Service Notice2
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Farkas, Scott