Date Filed | Summary | Pages |
09/09/2013 | Notice that the Delta-Wauseon Transmission Line Relocate Guying for North Star Steel Project was completed on approximately June 26, 2013 filed by T. Turner on behalf of FirstEnergy Service Company. | 1 |
01/03/2013 | OPSB Staff report of investigation filed by J. O'Dell, OPSB. | 1 |
12/17/2012 | Letter of Notification Delta-Wauseon 138kV Transmission Line Relocate Guying for North Star Steel York. | 14 |
12/17/2012 | Letters of notification sent to affected Counties filed on behalf of FirstEnergy Service Company by T. Turner. | 10 |
12/17/2012 | In the matter of the Letter of notification for the Delta-Wauseon 138 kV Transmission Line Relocate Guying for North Star Steel York Project. | 3 |