DIS - Case Record for 11-5582-EL-BNR Skip to main content

Case Record For:

11-5582-EL-BNR

Case Title: GREENFIELD/LAKEVIEW 138 KV TRANSMISSION LINE RECONDUCTORING PROJECT
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 11/1/2011
Date Closed: 3/20/2015
Printable Docket Card Service List
View All
1 - 4 of 4 documents 1 /  1 
Date FiledSummaryPages
03/20/2015Case Action Form to Close Cases effective 3/20/2015.6
06/04/2012Construction Notice of FirstEnergy Services Company, Greenfield - Lakeview 138 kV Transmission Line Reconductoring Project that project was completed on approximately May 17, 2012, filed by Scott M. Humphrys on behalf of FirstEnergy Services Company.1
11/23/2011Staff investigation report and recommendation filed by Staff, J. O'Dell.2
11/01/2011In the matter of the application of American Transmission Systems, Incorporated construction notice Greenfield-Lakeview 138 kv Transmission Line Reconductoring project. filed by Scott M. Humphrys. 22
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: