Date Filed | Summary | Pages |
12/04/2017 | Case action form closing cases with an effective date of 12/4/17 electronically filed by Mr. Jeffrey R. Jones on behalf of Public Utilities Commission of Ohio. | 2 |
05/03/2016 | Notice of Change of Address for counsel for the Ohio Power Siting Board, effective May 9, 2016. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board. | 3 |
12/03/2015 | Notice of Completion of Construction electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
09/30/2014 | Commencement of Construction - Phase II filed by Patrick Donlon on behalf of the Ohio Power Siting Board. | 1 |
12/23/2013 | Correspondence regarding Access Road Engineering Adjustment electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 2 |
10/11/2013 | Notice of Commencement of Construction electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 2 |
03/11/2013 | Service Notice | 2 |
03/11/2013 | Opinion, Order and Certificate stating that the Stipulation filed by the parties is approved and adopted and that a certificate be issued to AEP Transco for the construction, operation, and maintenance of the project at the preferred transmission line route. | 24 |
12/27/2012 | Transcript of AEP Ohio Transmission Company, Inc. hearing held on 12/13/12 before AE J. Tauber electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs. | 27 |
12/21/2012 | Exhibits for AEP Transmission Company, written statement by Chris McDaniel filed by Michael Spencer. | 5 |
12/20/2012 | Transcript of AEP Transmission Company hearing held Before Bryce A. McKenney, Administrative Law Judge, held at the Vinton County Community Building, 31935 State Route 93, McArthur, Ohio, on Thursday, December 6, 2012, at 6:00 P.M. electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. | 24 |
12/12/2012 | Proof of Pub for the Elk 138 kV Transmission Line Project filed in Jackson County Telegram and The Vinton County Courier electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 8 |
12/10/2012 | Proof of Pub Elk 138 kV Transmission Line Project (Vinton County) electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 5 |
12/07/2012 | Joint Stipulation and Recommendation electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 16 |
12/07/2012 | Direct Testimony of Shawn Malone electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 6 |