Date Filed | Summary | Pages |
04/18/2012 | Service Notice | 2 |
04/18/2012 | Finding & Order stating that each application be approved and the utility refund to the customer any assessed charges under the utility's EEDR rider during the exemption period approved by this order and OE motion for protective order is granted for 24 months from this issuance of this order. | 4 |
12/14/2011 | Staff Review and Recommendation electronically filed by Mr. Andrew S Conway on behalf of Staff. | 4 |
01/14/2011 | Motion for protective order and memorandum in support filed on behalf of Ohio Edison Company by K. Kolich. | 7 |
01/14/2011 | Confidential target for No-Load losses for McGraw-Edison Power Transformer filed by K. Kolich. | 1 |
12/30/2010 | In the matter of the application of Ohio Edison Company and General Motors LLC to Commit Energy Efficiency/Peak Demand Reduction Programs electronically filed by Mr. Kevin P. Shannon on behalf of Ohio Edison Company. | 42 |