Case Record For: 10-0204-RR-STP Case Title: CSX TRANSPORTATION INC Status: AR-Archived Industry Code: RR-RAILROAD Purpose Code: STP-State funded warning projects Date Opened: 2/18/2010 Date Closed: Case Documents Public Comments Parties of Record Related Cases Printable Docket Card Service List View All 1 - 12 of 12 documents 1 / 1 Date FiledSummaryPages 11/09/2012Case status form archiving case.1 09/15/2011Staff contacted CSX about the issues and CSX returned to the project site and made corrections to the project in May 2011. On August 30, 2011, an on site inspection was conducted by the PUCO. The crossing was determined to be in service and working to the requirements of the construction authorization (see attached field inspection report). Accordingly, the above case may be closed.6 09/15/2011Case status form to close case.1 09/14/2011Case action form re-opening case no. 10-204-RR-STP. 1 05/03/2011Case action form closing case with an effective date of 5/3/2011.1 04/25/2011Memo stating that a final inspection was conducted by the Rail Division on April 7, 2011. Basis of the attached final report for the grad crossing project, staff has determined that the project has been put-in service.5 12/09/2010Memorandum stating that the plans and estimates submitted by CSX have been reviewed and authorization for the Taylor project by the PUCO and ORDC is recommended, based on the stipulation outlined in the attached construction authorization filed by PUCO Staff.5 11/19/2010Service Notice5 07/21/2010Memo stating the plans and estimates have been reviewed and authorization of the Ringwood Rd project is recommended, filed by Staff. 5 03/03/2010Service Notice1 03/03/2010Entry ordering the stipulation is adopted and approved.5 02/18/2010In the matter of the request for CSX TRansportation, Inc. to install active grade crossing warning devices in Butler County, Oxford Township at Taylor Rd. (DOT #154-092R) and Ringwood Rd. (DOT #154-089H).16 1 / 1 Attorney General: Attorney Examiner: Lynn, James