Date Filed | Summary | Pages |
03/01/2011 | Service Notice | 1 |
02/28/2011 | Entry ordered that ATSI's request to withdraw this case be granted, that case 08-1028-EL-BNR be dismissed. | 2 |
02/04/2011 | Letter requesting to withdraw the construction notice submitted on August 27, 2008 for the Bayshore-Maclean-Lemoyne 138 kV Transmission Line Reconductoring Project in the above captioned case that was approved on September 27, 2008 filed by T. Krauss.
| 1 |
01/02/2009 | Correspondence stating that a typographical error occurred in the Construction Start letter dated December 15, 2008 for the Bayshore-Maclean-Lemoyne 138 kV Transmission Line reconductoring project, the correction is to the construction date, February 1, 2008, construction will begin January 2, 2008 should be changed to February 1, 2009 with construction beginning January 2, 2009 filed by FirstEnery by S. Humphrys. | 1 |
12/19/2008 | In response to the Construction Notice, construction on this project will begin on January 2, 2008 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
09/22/2008 | Staff investigation report and recommendation. | 1 |
08/27/2008 | In the matter of the construction notice of American Transmission Systems, Incorporated for Bayshore-Maclean-Lemoyne 138 kV transmission line reconductoring project. | 20 |
|