Case Title: HYATT/GENOA 138KV PERMANENT LINE RELOCATION
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 5/23/2008
Date Closed:
Printable Docket Card Service List
View All
1 - 5 of 5 documents 1 /  1 
Date FiledSummaryPages
01/16/2009Letter of notification that construction on the Hyatt-Genoa 138 kV Permanent Line Relocation Project was completed on or about January 10, 2008 filed on behalf of American Electric Power by S. Nourse.1
12/11/2008Notice that the construction on the Hyatt-Genoa 138 kV Permanent Line Relocation Project was completed on or about December 10, 2008 filed by S. Nourse on behalf of American Electric Power.1
08/20/2008Letter of notification of Columbus Southern Power Company dba American Electric Power stating that construction on the Hyatt-Genoa 138 kV permanent line relocation project is to be initiated on or about October 6, 2008 and completed on or about October 29, 2008 filed by S. Nourse.1
06/16/2008Investigation report and recommendation filed by PUCO Staff.1
05/23/2008In the matter of the application of American Electric Power, Columbus Southern Power for approval of the Hyatt-Genoa 138 kV Permanent Line Relocation for City of Westerville filed by S. Nourse.8
 