05/18/2010 | Memo closing case with an effective date of 05/18/10. | 1 |
01/22/2008 | Letter stating that the City of Shelby 2nd 138kV Interconnect project 138kV Transmission line to Shelby Northside Substation was completed and placed into service on December 20, 2007 filed by D. Niederkofler. | 1 |
02/23/2007 | Staff investigation report and recommendation filed by staff. | 1 |
01/16/2007 | In the matter of the letter of notification for The City of Shelby (Ohio) proposing the addition of a second single-circuit 138kV transmission interconnect between existing American Electric Power (AEP) Howard Substation located north of SR 61 in Sharon Township, Richland County and the City' s existing Northside Substation located on State Street within the Shelby Corporation Limits. | 48 |