DIS - Case Record for 06-0002-RR-FED Skip to main content

Case Record For:

06-0002-RR-FED

Case Title: CHICAGO, FT WAYNE & EASTERN RAILROAD, CSX
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 1/3/2006
Date Closed:
Printable Docket Card Service List
View All
1 - 10 of 10 documents 1 /  1 
Date FiledSummaryPages
01/19/2007Memo stating the grade crossing improvements/upgrades have been completed and are in service; cases closed of record.1
01/18/2007Service Notice3
01/17/2007Entry granting the request of NS for an extension of time to complete the project; that NS complete the project no later than August 9, 2007. 2
12/29/2006Memo recommending that the requested extension of time to August 9, 2007 to complete project be approved, filed on behalf of PUCO staff-Railroad Section.2
12/28/2006Request for extension of construction deadline and memorandum in support, filed on behalf of CSX Transportation, Chicago, Ft. Wayne & Eastern Railroad and Norfolk Southern Railway by D. Casey Talbott.6
06/15/2006Letter regarding the installation of automatic grade crossing warning devices at Stone Street in Fremont, Sandusky County filed by B. Sykes on behalf of Norfolk Southern Corporation.26
06/15/2006Letter regarding the installation of grade crossing warning devices filed by B. Sykes on behalf of Norfolk Southern Corporation.26
01/18/2006Service Notice.2
01/18/2006Entry ordered; that CFW, CSX, and NS submit to the Commission and ORDC site plans and cost estimates for the projects by April 18, 2006, that by April 25, 2006, CFW, CSX, and NS each file a letter in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates by ORDC, CFW, CSX, and NS proceed with construction of the projects, with construction to be completed by January 18, 2007; that CFW, CSX, and NS follow the detailed instructions as outlined on the ORDC letter of construction authorization, that CFW, CSX, and NS notify the Commission and ORDC 30 days before the projected date of completion; that at the time staff or ORDC makes its final inspection and if it finds that the installations are completed and have been put in service, staff will file a memorandum in this docket directing the docketing division to close this case of record.3
01/03/2006In the matter of the authorization of the Chicago, Ft. Wayne & Eastern Railroad, CSX Transportation and Norfolk Southern Railway to install active grade crossing warning devices at 4 locations in Ohio; Chicago, Ft. Wayne & Eastern Railroad; Allen County, near Elida, State Rd/CR 84, DOT # 532-736J. Norfolk Southern Railway; Sandusky County, City of Fremont, Stone St., DOT # 510-245Y, Lucas County, City of Toledo, Wheeling St., DOT # 851-539A. CSX Transportation; Lucas County, City of Toledo, Erie St, DOT # 867-099J.6
 
1 /  1 
      
      
Attorney General:
Attorney Examiner: