06/14/2005 | Entry ordering that W&T submit to the Commission and ORDC site plans and cost estimates for the project by September 15, 2005; that by September 22, 2005, W&T file a letter in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates by ORDC W&T proceed with the construction project to be completed by June 15, 2006; that the W&T notify the Commission and ORDC 30 days before the projected date of completion. | 3 |