Date Filed | Summary | Pages |
10/03/2005 | Report stating that warning device project has been installed in accordance with current design practices filed by PUCO staff. | 7 |
04/06/2005 | Letter stating that W&LE is now authorized to proceed with the field construction for the W&LE Grade Crossing Section Line Rd/CR30 (437-654N) Huron Co., filed on behalf of PUCO staff-Railroad Section-B. Johrendt. | 3 |
02/28/2005 | Letter stating that project plans and estimates were sent to PUCO filed by D. Reinsel on behalf of Wheeling & Lake Railway Company. | 1 |
12/08/2004 | Service Notice | 1 |
12/08/2004 | Entry stating that the subsidy stipulation is adopted and approved; that by March 8, 2005, W&LE submit site plans and cost estimates for the project; and by March 15, 2005 W&LE file a letter advising that it has submitted site plans and cost estimates; following approval of the site plans and cost estimates, W&LE proceed with and complete the project on or before December 8, 2005; that W&LE notify the Commission 30 days before the projected date of completion. | 4 |
11/12/2004 | In the matter of the request for upgrade of the warning devices at the Wheeling & Lake Erie Grade Crossing, Section Line Road/CR 30, Huron County. | 14 |