08/25/2004 | Entry ordered, that the Norfolk Southern Railway submit to the Commission and ORDC site plans and cost estimates for the project by 11/25/2004, that by 12/2/2004, NS Railway file a letter in this docketing advising that it has submitted site plans and cost estimates to the Commission and ORDC, that following approval of site plans and cost estimates by ORDC, NS Railway proceed with construction of the project, with construction to be completed by 8/25/2005, that NS Railway notify the Commission and ORDC 30 days before the projected date of completion. | 3 |