05/10/2005 | Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss. | 3 |
12/21/2004 | Letter stating that project has been delayed, is expected to begin on approximately on November 16, 2004 filed by T. Krauss on behalf of FirstEnergy Service Company. | 1 |
08/24/2004 | Staff Investigation Report and Recommendations filed on behalf of PUCO staff by J. O'Dell. | 1 |
07/30/2004 | In the matter of the American Transmission Systems for construction notice of the Avon-Emily 138kV Transmission Line Relocation Project Phase III for the State Route 82 Road Widening Project. | 13 |