Date Filed | Summary | Pages |
10/26/2006 | Letter stating that the grade crossing warning devises have been installed and are in service; that these cases be closed of record, filed by staff of PUCO. | 1 |
08/15/2006 | Service Notice | 1 |
08/10/2006 | Service Notice | 1 |
08/09/2006 | Entry ordered that I&O's extension request be granted;ordered that I&O complete the project by October 31, 2006; ordered that I&O notify the Commission and ORDC 30 days before the projected date of completion. | 2 |
07/19/2006 | Memo stating that the request by the Indiana & Ohio Railroad for an extension of time to complete one grade crossing project is well made and recommends that the request be granted, filed on behalf of PUCO staff-Railroad Section. | 2 |
07/18/2006 | Letter requesting an extension of time from August 31, 2006 to October 31, 2006, filed on behalf of the Indiana & Ohio Railroad by B. Konrad. | 1 |
12/21/2005 | Entry ordering that the extension of the construction deadline until August 31, 2006 be granted and that during the month of July 2006, I & O filed a status report on this project. | 2 |
12/21/2005 | Service Notice | 1 |
12/06/2005 | Letter requesting an extension of the completion for the active grade crossing warning devices at the intersection of Webster Ave. and Blue Ash Rd.until August 31, 2006 filed A. Satunas on behalf of Indiana & Ohio Rail System. | 1 |
12/06/2005 | Memo recommending that the Commission grants Indiana & Ohio Railroad the request for an extension of time filed by PUCO Staff. | 2 |
07/01/2004 | Service Notice | 1 |
06/30/2004 | Entry ordered; that I&0 submit to the Commission and ORDC site plans and cost estimates for the project by 9/30/2004, that by 10/7/2004, I&O file a letter advising that it has submitted site plans and cost estimates to the Commission and ORDC, that construction to be completed by 12/31/2005, that I&O follow the detailed instructions as outlined in the ORDC letter of construction authorization. | 3 |
06/30/2004 | Service Notice | 1 |
06/17/2004 | In the matter of the authorization of the Indiana & Ohio Railroad to construct an active grade crossing warning devise in Hamilton Co. | 3 |