Date Filed | Summary | Pages |
06/22/2004 | Letter informing Commission that construction of project was completed on 6/7/2004, filed on behalf of applicant by R. McElfresh. | 1 |
04/19/2004 | Construction notice informing date of April 12, 2004 to begin, filed by R. McElfresh. | 1 |
02/27/2004 | Staff Investigation report and recommendation. | 1 |
02/02/2004 | In the matter of the construction notice regarding a Cincinnati Gas & Electric Company project for the gas feeder line C 169 relocation project. | 10 |
|