Date Filed | Summary | Pages |
02/15/2005 | Memo closing cases of record, filed by PUCO staff-Railroad Section. | 1 |
01/19/2005 | Service Notice | 2 |
01/19/2005 | Entry ordering that the request for an extension of construction deadline until February 19, 2005 is granted; that the staff examine and recommend whether flagging should be required at this crossing until the project completion. (AA) | 2 |
01/19/2005 | Entry granting extension of construction deadline until February 19, 2005
electronically filed by Miller, Vesta on behalf of Alfred Agler, Attorney
Examiner, Public Utilities Commission of Ohio. (Hard copy filed January 19,
2005) | 3 |
01/14/2005 | Request for a one month extension of completion date filed by M. Connor of behalf of the Columbus & Ohio River Rail Road Company. | 1 |
01/14/2005 | Memo stating that staff is aware of attendant problems with this project from its inception, and noted in its memo docketed December 17, 2004 that further extension request might be made, therefore staff recommends that the extension be granted. | 2 |
12/17/2004 | Service Notice | 2 |
12/17/2004 | Memo stating that due to all the problems associated with this project, staff recommends that an extension for 30 days should be granted filed by G. Martin. | 2 |
12/17/2004 | Letter requesting an extension, one (1) month, to complete installation of equipment for signalization of SR 79 (USDOT 515 365 G) in Heath, Licking County, Ohio filed by M. Connor on behalf of The Columbus & Ohio River Railroad Company. | 1 |
12/17/2004 | Entry stating that the request for an extension of the construction deadline until January 19, 2005 is granted. (AA) | 2 |
11/18/2004 | Service Notice | 2 |
11/18/2004 | Entry ordering that an extension of the construction deadline until December 19, 2004 be granted; that staff examine and recommend whether flagging should be required at this crossing until the project completion. (SF) | 2 |
11/17/2004 | Letter requesting extension of time to install crossing gates filed W. Strawn II on behalf of Ohio Central Railroad System. (FAX) | 1 |
05/20/2004 | Service Notice | 1 |
05/19/2004 | Entry ordering that a six month extension of the construction deadline until November 22, 2004 is granted, that during the month of October 2004, C&O file a status report on this project, that staff examine and recommend whether flagging should be required at this crossing until the project completion. | 2 |