Date Filed | Summary | Pages |
10/21/2003 | Photos filed on behalf of applicant. | 10 |
10/09/2003 | Letter stating that, except for the removal of the electric transmission cable pipe from the Main Street Bridge, construction on this project was completed on October 3, 2003, filed on behalf of applicant by E. Truax. | 1 |
06/19/2003 | Letter stating that construction on this project is scheduled to start on July 7, 2003 and the company will notify the Commission when construction has been completed, filed on behalf of applicant by E. Truax. | 1 |
02/04/2003 | Investigation report approving the Letter of Notification, filed by L. Winget, OPSB staff. | 1 |
11/26/2002 | In the matter of the construction notice of American Electric Power-Energy Delivery, McComb-Central-Gay 138 kV Transmission Line public relocation project for Ohio Department of Transportation. | 4 |
|