Date Filed | Summary | Pages |
04/22/2004 | Letter of Notification to inform that KNG Energy is no longer the responsible party for the North Coast Gas Transmission pipeline and the project filed by S. Roller. | 1 |
09/03/2003 | Letter stating that an individual NPDES permit will need to be obtained for the discharge from the stormwater pond, filed on behalf of W. Ariss, Ohio EPA. | 1 |
07/17/2003 | Letter to Commission, filed on behalf of KNG Energy, Inc.- Buckeye 425 Compression Project by S. Howard. | 1 |
05/05/2003 | Letter stating that the project is now complete, filed on behalf of applicant by S. Roller. | 1 |
11/27/2002 | Response to Letter of Notification filed on behalf of the PUCO staff by K. Lambeck. | 1 |
11/27/2002 | Letter stating that the preliminary work on this project will begin the week of December 2, 2002; however, the planned date for actual construction of the first of the two compressor station sites will not be before December 5, 2002, filed on behalf of applicant by S. Howard. | 1 |
11/26/2002 | Additional information filed by T. Siguaw, Boots & Coots International Well Control, Inc. | 1 |
11/26/2002 | Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. | 1 |
11/13/2002 | Motion for waivers and memorandum in support filed on behalf of applicant by M. Petricoff. | 3 |
11/13/2002 | In the matter of the Letter of Notification of KNG Energy, Inc. to install two compressor stations to its Buckeye 425 Pipeline. | 160 |