Date Filed | Summary | Pages |
04/29/2005 | Letter of notification that the following CG&E projects were completed: Line C319 Pressure Improvement, date completed 8/11/02; Foster Warren 138kV adjustment completed 12/5/02; Miami Fort Morgan Junction Reconductoring completed 7/21/04, filed on behalf of applicant by S. Lane. | 1 |
10/17/2002 | Response to Construction Notice, filed by K. Lambeck, PUCO staff. | 1 |
10/17/2002 | Investigation report approving the Letter of Notification, filed by K. Lambeck, PUCO staff. | 2 |
10/16/2002 | Letter requesting an expedited review because the road construction schedule was moved up unexpectedly. Filed by Robert McElfresh. | 1 |
10/04/2002 | In the matter of Construction Notice on behalf of Cincinnati Gas and Electric Company project Foster Warren 138kv Hamilton Township Warren County, Ohio. | 7 |