10/16/2002 | Response to the letter of notification filed by T. Krauss on behalf of American Transmission Systems, Incorporated. | 1 |
08/30/2002 | Memo automatically approving the application with the effective date of August 30, 2002. | 1 |
07/23/2002 | Letter of Notification on American Transmission System, Incorporated's (ATSI) Clark-East Springfield 138kv Transmission Line Tap to AirPark Substation filed by T. Krauss. | 1 |
07/09/2002 | Response to Letter of Notification, filed by K. Lambeck, PUCO staff. | 1 |
07/09/2002 | Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. | 1 |
05/29/2002 | Motion for waiver of notice requirements for Letter of Notification, filed on behalf of applicant by M. Beiting. | 3 |
05/29/2002 | In the matter of the Letter of Notification of American Transmission Systems, Incorporated for the Clark-East Springfield 138 kV Transmission Line Tap to AirPark Substation. | 33 |