Date Filed | Summary | Pages |
10/16/2002 | Letter stating construction has been completed and initial energization is scheduled for 10/17/02 filed by S. Bloomfield. | 1 |
03/25/2002 | Response to S. Bloomfield to Letter of Notification, filed by K. Lambeck, PUCO staff. | 1 |
03/22/2002 | Investigation report approving the Letter of Notification, filed by L. Winget, PUCO staff. | 1 |
10/31/2001 | Letter confirming that copies of the Wetland Delineation and Threatened and Endangered Species Habitat Assessment Report was provided this day to Leon Winget, filed on behalf of applicant by S. Bloomfield. | 1 |
10/18/2001 | Letter stating that copies of the Phase I Cultural Resources Investigations of a Proposed Transmission Tower at the AEP Hanging Rock Substation, prepared by Gray & Page, and dated October 4, 2001, was provided this day under separate cover to Leon Winget, filed on behalf of applicant by S. Bloomfield. | 1 |
10/18/2001 | In the matter of the Letter of Notification of Ohio Power Company for the Hanging Rock 765 kV Substation. | 10 |