09/25/2001 | Letter stating that construction on this project has been completed, filed on behalf of applicant by J. Heppner. | 1 |
08/07/2001 | Letter stating that construction on this project is scheduled to start on August 6, 2001, filed on behalf of applicant by J. Heppner. | 1 |
08/03/2001 | Letter stating that construction on this project is scheduled to start of August 6, 2001, filed on behalf of applicant by J. Heppner. | 5 |
07/18/2001 | Investigation report recommending request be granted. (Filed 7/17/01) | 1 |
07/17/2001 | Response letter from Klaus Lambeck, PUCO, to John Heppner, AEP. | 1 |
06/01/2001 | In the matter of the Letter of Notification of Ohio Power Company for the Beverly 345 kV Extension Service to Washington Energy Facility. | 17 |