05/21/2002 | Letter stating that construction on this project is scheduled to begin on or about June 3, 2002, filed on behalf of applicant by G. Lamm. | 1 |
04/12/2002 | Letter Requesting a minor modification to the Letter of Notification due to a slight change in the proposed transmission line routing on behalf of Dominion Virginia Power, filed by G. Lamm. | 2 |
04/11/2002 | Response to the modification of the Letter of Notification, filed by K. Lambeck. | 1 |
12/05/2001 | Investigation report letter of notification. | 1 |
12/05/2001 | Letter of notification, filed by K. Lambeck. | 1 |
05/15/2001 | In the matter of the letter of notification of the Dresden Energy Facility concerning the required electric transmission for the facility. | 15 |