Case Title: TOLEDO EDISON/MIDWAY SUBSTATION
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BSB-Application for a certificate/ substation
Date Opened: 10/28/1997
Date Closed: 10/5/2001
Printable Docket Card Service List
View per page
Date FiledSummaryPages
10/05/2001Memo closing this case of record.2
10/16/2000ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates.13
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates 7
10/16/2000ICN #0029 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.)6
12/14/1998Letter stating construction of the 345-138 kV substation expansion portion was completed 11/2/98; 345kV transmission construction portion was completed 11/25/98; the Midway 345- 138 kV Substation Expansion was energized on 11/25/98 filed by G. Cunningham. (1 pg)1
09/30/1998ICN #0027 Letter to Mr. Gavin L. Cunningham stating that they may proceed with construction of the portion of the project as depicted on the drawings submitted on September 10, 1998, filed by K. Wissman, PUCO staff. (1 pg.)1
09/10/1998ICN #0026 Engineering drawings for the 345 kV transmission line portion of this project, filed on behalf of applicant by G. Cunningham. (5 pgs.)5
05/07/1998ICN #0025 Letter stating that construction for this project is scheduled to start on May 4, 1998, filed on behalf of applicant by G. Cunningham. (1 pg.)1
04/30/1998ICN #0024 Response letter to Mr. Gavin L. Cunningham regarding the engineering drawings, filed by K. Wissman. PUCO staff. (1 pg.)1
04/29/1998ICN #0023 Engineering drawings, Midway Site Improvements & Fence Plan, Drawing #5B649-202, Midway Property Drainage Improvements, Drawing #5B649-203, Midway Site Management & work Limits, Drawing #5B649-206, filed on behalf of appli- cant by G. Cunningham. (3 pgs.)3
04/29/1998ICN #0022 Engineering drawings, Overall Yard Electrical Assembly Plan, Drawing #5E649-172, Overall Yard Electrical Assembly Plan, Drawing #5E649-173, filed on behalf of applicant by G. Cunningham. (3 pgs.)3
04/29/1998ICN #0020 Transcript filed for hearing held 4/15/98, (SD), 9 pgs., Submitted. (PUCO-Columbus, OH)9
04/27/1998Opinion and Order ordering that the recommendations of the staff report of investigation, to which applicant has agreed by stipulation, be approved; ordered that the certificate be issued and contain the conditions set forth in section 4 of this order. (16 pgs)16
04/23/1998ICN #0018 Proof of Publication filed on behalf of appli- cant by C. Schraff and M. Beiting. (4 pgs.) (Hancock County)4
04/13/1998ICN #0004 Proof of Publication filed on behalf of appli- cant by C. Schraff and M. Beiting. (4 pgs.) (Henry County)4
04/08/1998Proof of Publication filed on behalf of applicant by C. Schraff. (13 pgs.) (Henry, Defiance, Hancock, Lucas Counties)13
03/31/1998ICN #0015 Staff Report filed. (46 pgs.)46
03/31/1998ICN #0014 Supplemental information filed on behalf of applicant by G. Cunningham. (2 pg.)2
03/26/1998Notice of substitution of counsel filed on behalf of applicant by C. Schraff and M. Beiting. (2 pgs.)2
03/25/1998ICN #0002 Supplemental information filing submitted on behalf of applicant by G. Cunningham. (2 pgs.)2
03/02/1998Proofs of Publication filed on behalf of applicant by M. Kempic. (15 pgs.) (Henry, Lucas, Hancock Counties)15
02/03/1998Entry scheduling the adjudicatory hearing at 10:00 a.m. on April 15, 1998, at the Commission offices; that the Board will accept petitions to intervene in the hearing by inter- persons up to five days prior to the scheduled date for the hearing or later. if good cause is shown, in accordance dance with Finding 8; that the Board will also accept and consider requests for a local hearing for this matter up to five days prior to the scheduled date for the hearing, if good cause is shown. (AE) (3 pgs.)3
01/30/1998Proof of service filed on behalf of applicant by M. Kempic. (3 pgs.)3
01/13/1998ICN #0008 Letter to Mr. Mark Kempic, Esq. informing him that the application has been certified as being complete in accordance with Ohio Administrative Code Rule 4906-1-14 (A) (1), filed on behalf of the PUCO staff. (2 pgs.)2
12/15/1997Replacements and additions to application filed on behalf of applicant by M. Kempic. (56 pgs.)56
11/20/1997ICN #0006 Entry ordering that this case shall be redesig- nated Case No. 97-1404-EL-BSB; that TE's motion for a waiver of the filing time requirement and TE's motion for a protective order are granted; that TE's motion for a waiver of the filing of ully developed information is denied at this time; that TE file, before December 15, 1997, normal load flow studies, which show system condi- tions (with and without the Midway expansion project) on the major substations in the area, and file, by December 15, 1997, the site selection study upon which it based the proposed sites in this application and the necessary alter- native site information; that the Docketing Divison of the Ohio Power Siting Board maintain, under seal, the unredact- ed diagrams of the October 28, 1997 application for 18 months from the date of this entry; that any party wishing to extend this confidential treatment should file at least 45 days in advance of the expiration date of this proective order. (AE) (4 pgs.)4
10/28/1997ICN #0005 Confidential portion of application filed on behalf of applicant by S. Hadick. (9 pgs.) (FILED UNDER SEAL)9
10/28/1997Motion for a protective order and memorandum in support filed on behalf of applicant by S. Hadick. (7 pgs.)7
10/28/1997ICN #0003 Motion for waiver of the requirement for fully developed information on the alternative site and memoran- dum in support filed on behalf of applicant by S. Hadick. (6 pgs.)6
10/28/1997ICN #0002 Motion for waiver of the requirement to file application one year prior to commencement of construction and memorandum in support filed on behalf of applicant by S. Hadick. (4 pgs.)4
10/28/1997ICN #0001 In the matter of the application of The Toledo Edison Company for a certificate of environmental compat- ibility and public need for the Midway Substation Expansion Project. (247 pgs.)247